Bund Design/Consultancy

Bund Design Consultants

When installing a bund it is essential that it is fit for purpose. There are many aspects to consider in designing a bund to ensure it is fully functioning and complies with regulations such as the Oil Storage Regulations and CIRIA 736.

Factors we consider during our bund design include:

Size/Capacity

The bund must be large enough to hold 110% of the capacity of the largest tank or 25% of the total storage, whichever is larger.

Dimensions

These will partly be dictated by the capacity requirements but will also need to take into account spigot flow/jetting failure and the tidal wave effect caused by catastrophic failure.

Wall height

This will also be largely influenced by capacity requirements however building a bund with particularly small walls make it more susceptible to the tidal wave effect, building a bund with tall walls can cause access issues, limit ventilation and make firefighting difficult.

Construction Material

It is preferable to construct a bund from concrete with an internal rebar structure, however in many circumstances well-constructed and lined brick built bunds will be sufficient and cost effective.

Specialist linings/coatings

It is usually recommended that bunds are lined with protective coatings to prevent the contained liquid from attacking the bund walls, this is especially important when the bund holds corrosive materials.

Automatic bund dewatering

For many sites, especially remote/unmanned sites, automatic bund dewatering devices can be installed to remove water from the bund but leave the contaminant contained.

Bund wall penetrations

Penetrations into bund walls for pipework or cables should always be avoided. Where they do occur it is essential they are effectively sealed using a methodology approved by site/industry requirements.

As you can see designing an effective and regulatory compliant bund is not a simple task. The requirements of the bund are bespoke to every situation and must be tailored to site specific conditions. As well as the points mentioned above you may also wish to consider additional controls e.g. where the bund is in a high traffic area you may look to install impact barriers.

We are experienced in designing bunds for all different sized tanks, a variety of liquids and for all different types of site e.g. COMAH, electricity substations, hospitals and factories.

Bund Design Technical Drawing

If you have an existing bund which you are concerned does not meet requisite standards or if a defect has been discovered by an external body e.g. environmental regulator or ISO 14001 auditor as well as designing new bunding we can also look to provide specifications for upgrading existing bunding to ensure it is fit for purpose and fully compliant to legislation.


Bund design case studies

bund design and construction

Extracts from Legislation & Guidance

"The container must be situated within a secondary containment system which satisfies the following requirements—

(a) subject to paragraph (5), it must have a capacity of not less than 110% of the container’s storage capacity or, if there is more than one container within the system, of not less than 110% of the largest container’s storage capacity or 25% of their aggregate storage capacity, whichever is the greater;

(b) it must be positioned, or other steps must be taken, so as to minimise any risk of damage by impact so far as is reasonably practicable;

(c) its base and walls must be impermeable to water and oil;

(d) its base and walls must not be penetrated by any valve, pipe or other opening which is used for draining the system; and

(e) if any fill pipe, or draw off pipe, penetrates its base or any of its walls, the junction of the pipe with the base or walls must be adequately sealed to prevent oil escaping from the system."

The Control of Pollution (Oil Storage) Regulations

If your tank is being installed in a constructed bund, the bund should be built using reinforced materials, with no damp-proof course and lined to ensure it is impermeable to oil.

Your bund should be designed to reduce the risk of oil spraying beyond the containment area if your tank developed a hole (known as jetting)......

A bund that is open to the elements should also have a sump formed in the base so you can remove rainwater for safe and legal disposal.

Above ground oil storage tanks: Guidance for Pollution Prevention 2 (GPP 2)

 

“The quality of design and construction is fundamental to the integrity of the containment system. It is therefore imperative that any designer, contractor or maintenance works operative engaged to construct, extend or modify a containment system is experienced in designing and constructing to the relevant class of containment. As a minimum, the parties should have a proven history of carrying out the relevant type of work.

All works need to be properly designed, whether it is the construction of a new or replacement bund, the extension or modification of an existing bund, or repair and maintenance work as set out in current standards.”

Containment systems for the prevention of pollution (C736)

Need advice for services and products? Call us now 01656 741 799

Geo Pollution Technologies (UK) LTD - company number - 04689357

ABOUT US

GPT head office is based in South Wales and covers all areas of South Wales, West Wales and Mid Wales including Cardiff, Swansea, Bridgend, Newport, Port Talbot, Powys, Llanelli, Neath, Pembrokeshire and Aberystwyth.

We also cover the South West of England from our premesis in Exeter including Cornwall, Devon, Taunton, Redruth, Truro, St Austell, Falmouth, New quay, Torquay, Paignton, Bristol, Plymouth, Bath, Gloucester and Somerset, .

We also operate across the midlands, London, Birmingham, Leicester, Northampton, Derby, Stoke, Nottingham, Coventry, Liverpool, Worcester, Southampton, Swindon, Manchester, Sheffield, Slough, Heathrow, Leatherhead and Surrey.